Mechanic’s Liens Mechanic’s liens and Lien Law trust claims.

A mechanic’s lien turns an unpaid construction invoice into a claim against the property itself. The Lien Law is strict on both sides: a lienor who misses a deadline loses the lien, and an owner who ignores one can find a sale or refinancing stalled.

We represent owners, developers, general contractors, subcontractors, and suppliers in filing, defending, bonding, and foreclosing mechanic’s liens and in trust fund claims under Article 3-A of the Lien Law.

Under Lien Law §§ 3 and 10, a contractor, subcontractor, laborer, or supplier who improves private property with the owner’s consent or at its request may file a notice of lien in the county clerk’s office where the property is located. The notice generally must be filed within eight months after completion of the contract or the final performance of work or furnishing of materials, and within four months where the property is improved or to be improved with a single-family dwelling. A copy must be served on the owner within five days before or thirty days after filing, and proof of service filed with the county clerk within thirty-five days after filing, or the notice terminates as a lien.

A lien does not last on its own. Under Lien Law § 17, it expires one year after filing unless the lienor commences a foreclosure action and files a notice of pendency, or extends it. On property other than a single-family dwelling, the lienor may file one extension for up to one more year; after that, and for single-family dwellings from the start, only a court order can continue it. An owner or contractor may discharge the lien from the property at any time by posting a bond or undertaking for 110 percent of the lien amount under § 19(4), which moves the dispute from the property to the security, or may petition to discharge a lien that is invalid on its face under § 19(6).

A lien the lienor has willfully exaggerated is void under § 39, and § 39-a makes the lienor liable for the owner’s bond premium, reasonable attorney’s fees, and the difference between the amount claimed and the amount actually due. Separately, Article 3-A makes construction funds received by an owner, contractor, or subcontractor trust assets held for those who furnished the work, and § 79-a makes a trustee and its officers who divert them guilty of larceny. On public improvements, a lien attaches to the unpaid contract funds rather than the property and generally must be filed within thirty days after completion and acceptance of the work.

Our capabilities include:

  • Preparing, filing, and serving notices of lien
  • Lien foreclosure actions and defense
  • Bonding and discharge of liens before closings and refinancings
  • Summary petitions to discharge facially invalid liens
  • Willful exaggeration claims under Lien Law §§ 39 and 39-a
  • Article 3-A trust fund diversion claims and accountings
  • Public improvement liens and payment bond claims
  • Building loan contract and lender priority disputes

Key Lien Law deadlines

File the notice of lienEight months after completion or last work or materials; four months for a single-family dwelling (§ 10)
RetainageNinety days after the retainage was due to be released (§ 10)
Serve the ownerFive days before to thirty days after filing (§ 11)
File proof of serviceWithin thirty-five days after filing (§ 11)
Foreclose or extendWithin one year after filing; extensions as § 17 allows
Public improvement lienWithin thirty days after completion and acceptance (§ 12)

Clearing a lien from the property

  1. Check the notice

    Compare the lien against the contract, the work, the dates, and § 9’s content requirements; a late or defective lien may be discharged summarily.

  2. Demand an itemized statement

    Under § 38, an owner may demand an itemized statement of the work and materials claimed.

  3. Bond it

    Post a surety bond for 110 percent of the lien amount and file it with the county clerk to free the property for a closing or loan.

  4. Shorten the clock

    Under § 59, serve a demand requiring the lienor to commence foreclosure within the time the notice sets, which must be at least thirty days.

  5. Litigate the amount

    Contest the claim in the foreclosure action and pursue exaggeration damages where the facts support them.

Key terms

Mechanic’s lien
A statutory lien on real property for the value or agreed price of labor or materials furnished to improve it.
Notice of lien
The document filed with the county clerk that creates a mechanic’s lien, with the contents § 9 requires.
Single-family dwelling
Property improved or to be improved with a single-family home, which has a four-month filing period and court-only extensions.
Retainage
A portion of contract payments withheld until completion, which carries its own ninety-day filing period.
Lien foreclosure
An action to enforce a mechanic’s lien, generally against the property or the security that replaced it.
Discharge by bond
Substituting a bond or undertaking for 110 percent of the lien under § 19(4), freeing the property.
Summary discharge
A court order under § 19(6) discharging a lien that is invalid on its face or untimely on the public record.
Willful exaggeration
Deliberately claiming more than is due, which voids the lien under § 39 and exposes the lienor to damages under § 39-a.
Itemized statement
A statement of the work and materials claimed that an owner may demand under § 38.
Building loan contract
A construction loan agreement that must be filed under § 22, or the lender risks subordination to mechanic’s liens.
Notice of lending
A filing under § 73 that protects a lender’s right to repayment from trust assets for advances made for an improvement.
Article 3-A trust
The statutory trust over construction funds received by owners, contractors, and subcontractors.
Trust diversion
Use of trust funds for non-trust purposes before trust claims are paid, which § 79-a makes larceny.
Public improvement lien
A lien on the unpaid funds of a public contract, filed with the public owner and its financial officer.

Questions we hear most

How long do I have to file a mechanic’s lien in New York?

Generally eight months after completing the contract or after the last work or materials were furnished, and four months for a single-family dwelling. A lien for retainage may be filed within ninety days after the retainage was due.

Can a contract waive my right to file a lien?

No. Lien Law § 34 makes an agreement waiving the right to file or enforce a mechanic’s lien unenforceable, although the statute permits a written lien waiver delivered at the same time as or after payment for the work, and a written agreement made after a lien is filed to subordinate, release, or satisfy it.

The lien is on my property but I paid my general contractor in full. Is the subcontractor’s lien valid?

A subcontractor’s lien is generally limited to amounts earned and unpaid under the owner’s contract with the general contractor when the lien is filed, plus amounts earned under that contract afterward. If the owner paid in good faith before the lien was filed, there may be little or nothing for it to attach to.

What happens if the lienor never sues?

The lien expires one year after filing unless the lienor starts a foreclosure action with a notice of pendency or extends the lien as § 17 permits, and the owner can then have it discharged of record.

Who can file a mechanic’s lien?

Contractors, subcontractors, laborers, material suppliers, and certain others listed in Lien Law § 3 who improve real property with the consent or at the request of the owner or the owner’s agent, contractor, or subcontractor. The lien is limited to the value or agreed price of the work, not damages such as lost profits on unperformed work.

Can a tenant’s contractor lien the landlord’s building?

Only if the owner consented to the improvement in a way the law recognizes, which generally requires more than mere knowledge or a lease permitting alterations. Otherwise the lien may attach only to the tenant’s leasehold interest.

Do I have to foreclose within a year if the lien has been bonded?

The bond replaces the property as security, but the lienor still must enforce its claim within the time the Lien Law and the bond allow. A bill that would change the duration of bonded liens, A10682-A and S10033, passed the Assembly in May 2026 but had not passed the Senate or been enacted as of November 2026.

What is the risk of filing a lien for too much?

If a court finds the amount was willfully exaggerated, the entire lien is void and the lienor can be liable for the owner’s bond premium, attorney’s fees, and the excess claimed. An honest mistake or a good-faith dispute over the amount is not willful exaggeration.

Can trust fund claims reach the owner or contractor’s officers personally?

Officers, directors, and agents who knowingly participate in a diversion of Article 3-A trust funds can be held personally liable, and § 79-a also provides for criminal liability. Failure to keep the required trust records is presumptive evidence of diversion.

Does a lien survive a sale of the property?

Yes. A properly filed and served lien remains attached to the property after a sale unless it is bonded, paid, or discharged, which is why title companies require liens to be cleared before closing.
Contact

Tell us about your dispute

Whether you are a tenant facing eviction, an owner with a non-paying or non-compliant tenant, or a party to a contract that did not close, we welcome the conversation. Initial consultations are complimentary. If a court date is approaching, please include it in your message.

Send inquiry

Tell us about the matter and we will respond within one business day.

Confidential. Submitting this form does not create an attorney-client relationship. We respond within one business day.

Skip to main content