Published

Not legal advice. This article is general information about New York law. Reading it does not create an attorney-client relationship. For advice about your situation, consult a lawyer.

What approvals are needed for battery storage and EV chargers in NYC buildings?

A stationary battery system generally needs an FDNY Certificate of Approval for the equipment and a DOB construction permit for the installation. Indoor systems, and outdoor systems over 20 kWh in aggregate, also need an FDNY permit and commissioning inspection, renewed annually. EV chargers need a licensed electrician and electrical permits, and Local Law 55 of 2024 requires charging in a share of spaces at covered garages and lots.

Battery storage: the approval path

In New York City, battery energy storage systems are regulated by the Fire Department under Fire Code § 608 and FDNY Rule 3 RCNY § 608-01, and by the Department of Buildings under the Construction Codes and 1 RCNY § 101-19. FDNY’s April 2025 equipment approval and installation guide summarizes the process:

  • Equipment approval: the battery product needs an FDNY Certificate of Approval. Outdoor stationary units of 2 kWh or less per unit are exempt.
  • Construction approval: every stationary installation needs a DOB construction permit. DOB requires full plan examination and does not accept professional certification for these filings.
  • Site review: DOB’s site-specific evaluation calls for the product listing, full-scale fire testing, the Certificate of Approval, a battery plan set, and, where required, FDNY conditional acceptance and a commissioning plan.
  • FDNY permit: indoor systems, and outdoor systems over 20 kWh in aggregate, need an FDNY permit and a commissioning inspection that includes an emergency shutdown test. The site permit lasts one year and is renewed after inspection. One- and two-family homes are exempt from the FDNY permit.
  • Personnel: a Certificate of Fitness holder must be responsible for the installation and present at commissioning.
  • Registration: the system must be registered with DOB before it begins operating.

Rooftop systems raise added questions, including roof access under the Fire Code and, in some cases, additional fire detection. Location, size, and battery chemistry drive cost and schedule, so involve an engineer with storage filing experience before signing an equipment contract.

EV chargers: permits and parking rules

Level 2 and DC fast chargers require work by a licensed electrician, electrical permits, and often a service upgrade from the utility. Before committing, find out whether the building’s service can carry the load or whether load management can share capacity among chargers.

Local Law 55 of 2024 sets requirements for parking facilities with 10 or more spaces. New and significantly altered garages and open lots must equip 20 percent of spaces with Level 2 chargers and make 60 percent capable of supporting charging. Existing garages and lots licensed by the Department of Consumer and Worker Protection must reach 20 percent equipped and 40 percent capable by January 1, 2035. One DC fast charger counts as 10 Level 2 chargers, for up to half the requirement, and waivers are available for structural, cost, and vertical-parking constraints. Requirements for unlicensed facilities are to be set by DOB rule.

Utility and state incentives can offset costs. New York’s utilities, including Con Edison, administer the statewide EV Make-Ready Program under Public Service Commission orders, and NYSERDA has offered incentives for storage. Program terms and funding change, so confirm current availability before budgeting.

Local Law 97 interplay

Local Law 97 counts electricity toward a building’s emissions, so adding chargers or electrifying heat can increase reported electricity use even as fuel use falls. A battery does not reduce consumption, but the law allows deductions for clean distributed energy resources, including storage, based on their ability to reduce emissions during designated peak periods. In Buildings Bulletin 2025-014, issued December 8, 2025, DOB explained how buildings that host storage, or that buy energy from a storage system, including one located off site, can calculate those deductions. Model the deduction before relying on it in a compliance plan.

Insurance and risk

  • Notify the property insurer before installation. Some carriers impose conditions or exclusions for lithium-ion systems.
  • Require installers and third-party system owners to carry general liability, property, and pollution coverage naming the building owner as additional insured, with waivers of subrogation.
  • Assign responsibility for monitoring, maintenance, annual FDNY inspections, and the emergency management plan.
  • Address warranties, battery degradation, and end-of-life removal and disposal.

Third-party ownership and leases

Many storage and charging projects are owned by a developer under a site lease, license, or energy services agreement. Those contracts should cover term and removal, who holds the permits and handles FDNY inspections, access, revenue from charging fees and demand response, which party receives any Local Law 97 deduction, insurance and indemnity, lender consent, and what happens if the building is sold.

In commercial buildings, the lease should say whether a tenant may install chargers or batteries, who owns them, who pays for electricity, and how emissions benefits and penalties are shared. Many owners address these points in green lease provisions.

Condos and co-ops

Real Property Law § 339-ll, part of the Condominium Act, voids bylaws and other instruments that effectively prohibit or unreasonably restrict an EV charger in a unit owner’s unit or designated parking space. The board may impose reasonable restrictions that do not significantly increase cost or reduce performance. If the board does not deny an application in writing within 60 days, it is deemed approved. The owner pays for installation and electricity, must use a licensed contractor, and must carry insurance naming the association. Co-op installations are governed by the proprietary lease, house rules, and board approval.

Not legal advice. This article is general information about New York law as of the date above. It is not legal advice, may not reflect later changes, and does not create an attorney-client relationship. Attorney advertising.