What should New York landowners know before leasing land to a data center?
Data center deals are usually ground leases, powered shell leases, build-to-suit leases, or sales, often preceded by a long option period. Power availability drives value and timing. Executive Order 62 holds DEC discretionary permits for data centers of 50 megawatts or more pending a statewide environmental review, but local zoning and IDA incentives are not paused. Owners should negotiate term, renewals, expansion rights, utility responsibilities, decommissioning, and restoration security.
Why data center users want land
Cloud computing and artificial intelligence workloads require large, reliable electric service, and developers now choose sites based on available power as much as on location. In February 2026, the Governor’s office reported that the New York Independent System Operator’s interconnection queue held 48 large-load projects totaling more than 11 gigawatts as of January 2026. For an owner of acreage near transmission lines, a former industrial site, or a building with heavy electrical service, that demand can produce an unsolicited offer. It can also produce a long, conditional process in which the developer holds the property off the market while it tests whether power can be delivered.
Common deal structures
| Option to lease or purchase | The developer pays option fees for the right to lease or buy later while it studies power, zoning, and permitting |
|---|---|
| Ground lease | The owner leases the land; the tenant builds and owns the improvements during the term |
| Powered shell lease | The landlord delivers a building with core structure and utility service; the tenant installs power distribution, cooling, and IT equipment |
| Build-to-suit lease | The landlord builds to the tenant’s specifications under a long-term lease with detailed delivery obligations |
| Sale | The owner sells outright, usually with contingencies tied to power and approvals |
A powered shell or build-to-suit places construction and delivery risk on the landlord, including the risk of delay credits or termination if power or the building is late. A ground lease leaves more of that risk with the tenant but leaves the owner with a long-term encumbrance on the land. The choice affects financing, taxes, and how much control the owner keeps.
Power and interconnection
Power is usually the gating item. A large load typically needs a utility service study and often new substations or transmission upgrades, and the timing is set by the utility and the grid operator, not by the parties. In February 2026, the Public Service Commission opened a proceeding, Case 26-E-0045, on how large loads such as data centers connect to the grid and how upgrade costs are allocated, as part of a Department of Public Service initiative called Energize NY Development. The rules on cost responsibility are still being developed.
That uncertainty belongs in the contract. Option periods should be finite, with escalating extension fees. The agreement should say who applies for utility service, who pays for studies and upgrades, who controls easements granted to the utility, and what happens to those easements and to the developer’s studies if the project does not proceed.
Executive Order 62 and state environmental review
On July 14, 2026, Governor Hochul signed Executive Order 62. It directs the Department of Environmental Conservation to hold in abeyance applications for discretionary permits to build or expand data centers that use, or can use, 50 megawatts or more, until the Department of Public Service completes a generic environmental impact statement under SEQRA. Applications deemed complete before July 14, 2026 are not held, and facilities used primarily for manufacturing, research, education, or medical care are excluded. The order has no fixed end date and does not apply to local government permits.
On September 17, 2026, the PSC issued a positive declaration and a draft scope for that review, with comments due October 20, 2026. Owners negotiating with large-load users should expect longer approval timelines and should reflect the order in contingencies, outside dates, and option extension terms.
Zoning and local approvals
Data centers raise familiar land use questions: whether the use is permitted in the district, height and bulk limits for rooftop cooling equipment, backup generators and fuel storage, noise, water use, and construction traffic. In New York City, the Zoning Resolution and the Construction Codes govern. Elsewhere, the town or village code controls, and discretionary local approvals require SEQRA review. Backup generators may need air permits. A municipality can also adopt its own moratorium, so check the local record before granting a long option.
Tax incentives
Many projects seek benefits from a local industrial development agency under General Municipal Law Article 18-A, such as a payment-in-lieu-of-taxes agreement, sales tax exemptions on construction materials and equipment, and a mortgage recording tax exemption. IDA benefits are discretionary, require a public hearing, and usually include recapture if the project falls short of its commitments. To make the structure work, the IDA typically takes a leasehold or other interest in the property, so the owner must sign on. The lease should make the tenant responsible for all taxes and PILOT payments and should indemnify the owner against recapture.
Lease terms owners should negotiate
- Term and renewals: long initial terms with tenant renewal options are common. Decide whether renewal rent is a fixed increase or a reset to fair market value.
- Rent: fixed annual escalations, and rent commencement on a fixed date rather than when the tenant’s power is energized.
- Expansion rights: rights of first offer or refusal on adjacent land should be limited in time so the rest of the property is not frozen.
- Utilities and easements: who grants them, who pays, and whether they survive the lease.
- Environmental: fuel storage, hazardous materials, water use, and environmental indemnities.
- Decommissioning: removal of buildings, generators, tanks, and underground conduit at the end of the term, secured by a letter of credit or bond.
- Credit: the tenant entity is often a single-purpose company, so require a parent guaranty or other credit support.
- Financing: leasehold mortgage provisions that protect the tenant’s lender without subordinating the owner’s fee.